Back to Projects

Project Summary

  • EPC:    Dragados 
  • LOCATION:   Germany
  • TIMELINE:   October 2022 to 2025
  • END USER:   TenneT & Amprion

Project Overview

Dragados Offshore, S.A. in Consortium with Siemens Energy Global GmbH & Co. KG, will design build and install three (3) 2GW HVDC offshore windarm energy converter stations (BalWin3, LanWin2 and LanWin4) in the North Sea for TenneT the Dutch / German transmission system operator.

Dragados Offshore, S.A. in Consortium with Siemens Energy Global GmbH & Co. KG, will develop, build and deliver the HVDC Grid Stations for both BalWin1 and BalWin2 Projects for Amprion Offshore GmbH. Each project consists of a 2-Gigawatt HVDC Offshore and Onshore Station for the transmission of energy.

Project Scope

Nessco scope of work includes:

  • Dynamic Positioning System Option
  • ATIS
  • Navaids
  • Weather Monitoring
  • FO System
  • VSAT
  • PAGA
  • LAN/WAN, Telephony, PBX, Mobile Network
  • CCTV
  • DACS
  • LOS Hardware
  • VHF Radio & GMDSS
  • DMR Radio
  • Basic and Detailed Design, Sourcing, Build Integration, FAT, Site Commissioning, SAT